Minutes of
Community Liaison Group Meeting No. 2
held on Thursday, 29
June 2006
Meeting opened 5.15 pm
Present:
|
John Dengate - Chairman |
Shaun Reason -Windang Beach Tourist Park |
|
Clr John Leedham - Shellharbour City Council |
Justin Kennedy - Dept of Commerce |
|
Ron Hales - LIA |
Chris Brandis - IBOC |
|
Leon Cicolini - Community |
Alan Beveridge - Warilla Surf Life Saving Club |
|
Bob Prospero - SLIAG |
Craig Rogers - Director, Coastwide Civil |
|
Barry Hennessy - Community |
Michael Wooley - URS Australia |
|
Mike Malone - Wollongong City Council |
Garry Clarke - Dept of Natural Resources |
|
Doug Prosser - LIA |
Shirley Massey - Commercial Fishers |
|
Michael Westra - Wavesailors |
|
Apologies: Greg Amadio, Wayne Lenardon, Tony
McCabe, Bob Rawlinson, Bill Young, Garth Bridge.
1. Introductions & check in
Michael Westra (Wavesailors and Surfers) introduced
himself and briefly explained his group’s interest in the entrance
works. Concerned about the height of the walls and impact on wave
sailing activities. Expect new walls however will improve surfing
conditions.
Each attendee checked in with a comment re their
feelings on progress to-date.
2. Previous minutes
Noted that Garth Bridge was omitted from meeting 1
minutes - to be added
Q. Will the extension of the groyne at Elliot
(Little) Lake be done as part of this activity and be completed prior to
beach nourishment works commencing?
A. Garry Clarke advised that the work at Elliot
Lake is being funded as part of a separate NSW Government grant to
Shellharbour City Council. A decision will be made soon as to whether or
not the work will be completed as part of the current entrance contract
or managed by the council. Depending on timing, the groyne may be
completed before beach nourishment works begin.
Doug Prosser moved that minutes be accepted.
3. Project update - Garry Clarke (DNR) and
Craig Rogers (CWC)
Rock structures
- The Construction Environmental Management Plan
(CEMP) has been signed-off by the Department of Planning and all other
required approvals are in place. The environmental management
representative (EMR) will assess performance against the CEMP on an
ongoing basis.
The CEMP will be put on
the LIA’s entrance activity website.
- Signs explaining the work will be erected
shortly at three locations:
- Entrance to haul road - north side.
- Reddall Parade - near kiosk, and at
eastern-end car park on southern side.
- There was an on-site announcement by Minister
Campbell on 22 June 2006, with a symbolic placing of the
first rock and appropriate media coverage.
- Coastwide Civil has commenced work. GPS tracking
is being used in the construction equipment to guide the work.
- Excavation is underway for the initial section
of the northern wall, with excavation depth of about 2-2.5 metres.
- Both breakwaters will be built simultaneously,
with rock being imported as required from the quarry stockpile and
Dunmore Tip.
Dredging and beach nourishment
- LIA is currently finalising the contract,
intending to call for tenders in July, award the tender in September,
and commence work in November 2006. The channel length is to be
extended upstream by about 300 metres to Berageree Island from that
shown in the EIS (dates are indicative at this stage).
Q. What is the final channel width?
A. Garry Clarke advised that due to the extension
of length channel to be dredged, it was anticipated that some reduction
in width may be required ie from 100 metres to approx 75 metres. Recent
calculations by the design consultant indicate an 100-metre wide channel
can be maintained providing the side batters are steepened and reduced
in width. The amount of sand to be removed remains at 200,000 cubic
metres.
Doug Prosser advised that as experienced with
dredging the channel for the southern breakwater, the sand mass east of
the bridge is extremely mobile. Therefore channel widths and depths may
vary after the initial dredging is complete.
Q. Where will the sand go?
A. Garry Clarke advised the sand from the current
excavation for rock placement will be redistributed around the wall area
and Perkins Beach dune. All the dredged sand from the channel will be
pumped to Warilla Beach along the seawall.
Q. Warilla Beach is hosting a State wide surf
carnival on 4th November, and a large South Coast carnival on
5th November 2006. Discharge of sand to the beach area during
this time may adversely effect carnival activities. Alan Beveridge
asked if this could be considered with regard to the dredging and
associated pumping for beach nourishment.
A. Garry Clarke advised the LIA will add that
requirement to the contract, to ensure minimal impact.
Alan Beveridge to provide a letter to the LIA by 7th
July 2006, outlining the Surf Club’s requirements with respect to the
carnivals.
Q. What access is available to the construction
area?
A. Craig Rogers advised that access is restricted
to the whole construction area- designated by the orange fences- to
ensure safety to the public. This is a strict Occupational Health and
Safety (OH&S) requirement.
Q. How far does the wall extend offshore?
A. Garry Clarke advised approximately 200 metres.
The artist impression sent with last minutes shows more sand than is
currently the case – shows the expected build-up of sand over time
against the outer edge of the northern wall.
Q. What work is occurring on weekends?
A. Craig Rogers advised that work will be limited
to Saturday mornings from 8am to 1pm. There will be no transport of
rock on weekends.
4. Environmental performance - Garry Clarke and
Craig Rogers
- Noise levels are being monitored routinely at
selected locations- truck and equipment. Results so far show:
- Trucks- highest reading 75 dB (at 5m distance)
- Machinery- highest 85 dB (at 5m distance)
- Pump- approx 70 dB. A physical barrier (sand
wall) is also being used. Pumps are being run 24hrs to keep the
excavation dry for the initial wall construction across the sand.
Delays would be experienced unless the 24 hr pump operation is
maintained.
- Back ground noise level taken at the site at
4pm on 29/6/06- approx 60 dB
- Noise level criteria at nearest residence is
to be 57 dB (approx 300m from work site)
- Air Quality- monitored for dust and exhaust
emissions
- Water Quality- turbidity monitored- no issues
5. EMR report - Michael Woolley, URS Australia
Michael Woolley reported that he has reviewed the
CEMP, and also undertaken a site inspection- no issues reported. He
will be visiting the site every 2 weeks.
6. Complaints procedure
A toll free number has been established by the LIA
for issues and complaints- 1800-467 377.
A procedure outlining the protocols for response
and follow-up has been established by the LIA (copy attached),
Response is to be provided within 24 hrs during
office day time and 2 hrs after hours.
There was a suggestion to add the address of the complainant to the
spreadsheet.
7. Two-way information flow
There was satisfaction expressed with both the
information available on the website, as well as the information
provided by Garry Clarke following the meeting. It was requested that
this continue, and also that group members receive media releases as
they are issued.
Shirley Massey provided an example of how she was
passing the information on to her constituents (Commercial Fishermen)
via their newsletter (copy attached). Shirley Massey was congratulated
on her initiative.
Little feedback had been received so far from
others via the group members. Each member will provide feedback as they
receive it.
8. Media protocols
The group indicated that the LIA should act as
spokesperson for the group around media queries. The LIA is responsible
for the group. It was understood that each member has the obvious right
to comment on their own and their group’s views and perspectives, but
that it made sense that there was one voice from the CLG.
9. Site visits
The group discussed the value of periodic site
visits to view progress. It was agreed to schedule bi monthly site
visits at 4pm prior to the scheduled CLG meeting, starting with the July
meeting. If significant progress has not been made, the site segment may
be postponed, and will be advised via the agenda papers.
Meeting closed 6.05 pm
Next meeting: 4 pm, Thursday 27 July 2006, site
visit (meet at Windang Surf Club car park), followed by 5 pm meeting at
Windang Senior Citizens Hall.